Сonnection to engineering networks

Connection of the capital construction object to the systems of electricity, heat, gas, water supply and water disposal

Electricity

Find the network organization whose power grid facilities are located at the smallest distance from the site boundaries. Сontact for technical specifications and the draft connection contract.

For more information, please click here: https://www.mos.ru/services/advisor/story/podklyuchenie_k_inzhenernym_setyam/1/13/

Gas distribution

If the maximum hourly gas flow rate does not exceed 300 cubic meters. M, you can sign a connection contract without first providing technical specifications. In other cases, for connection to gas networks, it is necessary to obtain technical connection conditions.

For more information, please click here: https://www.mos.ru/services/advisor/story/podklyuchenie_k_inzhenernym_setyam/1/29/

Cold water supply, water treatment

Connection to the networks of cold water supply and water disposal in Moscow is engaged in “Mosvodokanal.”

During the connection, you will need to go through the following steps:

  • conclusion of the contract for connection, including the terms of connection;
  • Implementation of a complex of construction and installation works for the construction of cold water supply and (or) sewerage networks and signing of acts on the implementation of technological connection.

For more information, please click here:
https://www.mos.ru/services/advisor/story/podklyuchenie_k_inzhenernym_setyam/1/18/

Heat supply and hot water supply

17.07.2017