Reference object is ready for commissioning

30.12.2016

The Podium Market company has completed the main construction process and documentation for commissioning the reference object. The project is passing through the 8th stage out of 9 – submission of documents for obtaining an occupancy permit.

As part of the project implementation the 6th and 7th stages were completed on December 28-29: application to UATI (Union of Administrative Technical Inspections) for closing the order on excavation works was submitted, and the procedure of connecting the reference object to Mosvodokanal networks was completed.

As a result the latter procedure, one of the most time-consuming, was passed through in 26 days – 4 days faster than the planned target.

Now the developer has already initiated the 8th stage – it has submitted documents for obtaining the occupancy permit. Processing an application takes 10 working days, that means the documents should be ready on January 17, 2017.

It is to be recalled that the Podium Market company has launched a new project in April 2016. A new project of construction a warehouse complex class B+ has launched near the end station Salaryevo of Sokolnicheskaya metro line. In a co-project “Test purchase” with PH “Kommersant” the company decided to check the operation of the new system of getting approvals and permits. Due to the reforms on lowering administrative barriers implemented by the Moscow government such king of projects can be completed in “9 Steps”.