The OEK cut the terms of connection to electricity networks

“United Energy Company” is connecting to electricity supply networks in Moscow for 90 days. This was reported to the journalists by the Deputy General Director for the implementation of the company’s services Irina Silayeva.

“We are ordered to issue a contract for 10 days, 70 days to build and 10 days to conduct all procedures for processing documents,” she said.

Optimization of the procedure for technological connection was carried out by the OEC in the framework of work to improve Russia’s position in the World Bank’s Doing Business ranking in the direction “Connecting to Electric Grids”.

Recall, connection to power supply systems is evaluated by the bank’s experts in three parameters: the complexity of the procedure, the time and money.