Sergey Boldyrev: GPZU for construction of warehouse can be obtained in 27 days

03.08.2016

boldyrev“The city authorities have adopted a number of resolutions aimed at simplifying administrative procedures in the field of construction for low-risk facilities. So we managed to obtain GPZU (development plan of a land plot) for construction of a warehouse complex in New Moscow for 27 days instead of 30 days established by the current legislation,” said Development Director of Podium market company, coordinator of the project “Test purchase” Sergey Boldyrev.

According to him, today it is possible to build such a warehouse in Moscow in 9 steps, spending only 99 days for all the administrative procedures.

“In the framework of the project “Test purchase” our company decided to test whether these figures correspond to reality. Our company has successfully passed three steps out of nine. So, the developer has already obtained GPZU, construction permit and the excavation order. Still 6 steps are ahead,” said Sergey Boldyrev.